shivram enclave phase -3

PCGRERA081021001279 Janjgir-Champa New Residential Plotted Development Partial Compliance
Compliance Status Based on public CG-RERA records
3 Passed
1 Issue(s)
2 N/A
RERA Registration Active
Reg No. PCGRERA081021001279 — Status: New
No RERA Orders
No complaints or orders found against this project
Sec 38–63 · Source
No Orders in Last 12 Months
Clean record — no complaints or orders filed
Completion Overdue
Was due 26 Dec 2024 — overdue by ~17 month(s)
Section 4 · Source
Quarterly Updates Not Available
No compliance snapshot data on record
Section 11 · Source
Annual Audit Not Available
No compliance snapshot data on record
Section 4(2)(l)(D) · Source
Each check is based on publicly available CG-RERA portal data as of May 2026. How this works →
At a Glance
21
Total Units
14
Units Sold
4
Unsold
0
Legal Cases
Dec 2024
Target Completion
100%
Completion
Other Projects by Same Promoter (2)
ProjectRERA No.StatusDistrictType
SHIVRAM ASHIRVAD PCGRERA160718000558 Ongoing Janjgir-Champa Plotted Development
SHIVRAM ENCLAVE PHASE 4 PCGRERA310725001953 New Janjgir-Champa Residential Plotted Development
Registration Details
RERA Number
PCGRERA081021001279
Status
New
Project Type
Residential Plotted Development
EWS Category
NO
Construction Cost
₹ 7100000
Land Cost
₹ 3743000
Proposed Completion
26 Dec 2024
Authorised Person
rakesh gupta
Website
www.shivramashirvad.in
Professional Team
RoleNameLicense / Membership
Statutory CA Ankita Agrawal 180201
Quarterly CA Mayank Saraf 177706
Engineer VAIBHAO KESHARWANI 370
Architect ABHISHEK SHRIVASTAVA 146 CA/2008/43810
Promoters
R
RAKESH GUPTA Individual
Location Details
Address
VILLAGE - NAILA TAHSIL- JANJGIR ,DIST- JANJGIR CHAMPA
District
Janjgir-Champa
Tehsil
Janjgir
Coordinates
22.0139436, 82.5598577 View on Map
Amenities (8)
BOUNDARY WALL
100%
INTERNAL ROADS AND FOOTPATHS
100%
LANDSCAPING AND TREE PLANTING
100%
SEWERAGE
100%
STORM WATER DRAINS
100%
STREET LIGHTING
100%
WATER CONSERVATION RAIN WATER HARVESTING
100%
WATER SUPPLY
100%
Neighborhood Intelligence

Explore nearby infrastructure around this project. Toggle categories to show/hide on the map.

Neighborhood Map 3 km radius
RERA Projects Near shivram enclave phase -3 9 found within 3 km
# Project District Status Distance
1 SHIVRAM ENCLAVE PHASE 4 Janjgir-Champa New 0.06 km
2 TIRU HOMES Janjgir-Champa Ongoing 0.53 km
3 SHRI NAHARIYA BABA CONSTRUCTIONS PHASE -II Janjgir-Champa Ongoing 1.01 km
4 OM BHUMI Janjgir-Champa New 1.03 km
5 meena paliwal Janjgir-Champa New 1.06 km
6 B.M. ENTERPRISES-II Janjgir-Champa New 1.07 km
7 SHRI NAHARIYA BABA CONSTRUCTIONS PHASE -III Janjgir-Champa New 1.08 km
8 B M ENTERPRISES Janjgir-Champa Ongoing 1.08 km
9 MAA MARKET Janjgir-Champa Ongoing 1.34 km
Buyer Document Verification Checklist

Key documents a buyer should verify before purchasing in this project. Items marked Available have data on Seemankan.

7/14 verified
  • RERA Registration Certificate Available
    Confirms the project is registered with RERA CG. Verify registration number, validity dates, and project details on the RERA portal.
    RERA No: PCGRERA081021001279
  • Promoter Registration Certificate Verify Independently
    Builder / colonizer company registration certificate. Confirms the promoter entity is a registered firm, company, or society.
  • Approved Building / Sanction Plan Verify Independently
    Building plan sanctioned by the local authority. Verify floor count, setbacks, and FSI compliance.
  • Layout Plan Verify Independently
    Approved layout showing plot divisions, roads, open spaces, and common areas.
  • Title Deed / Ownership Proof Verify Independently
    Proof that the promoter legally owns the land. Verify via Sub-Registrar records.
  • Encumbrance Certificate Verify Independently
    Confirms the property is free from legal dues, mortgages, or liens. Obtain from Sub-Registrar office.
  • Land Use / Diversion Certificate Verify Independently
    Required if land was converted from agricultural to non-agricultural use.
  • Architect Certificate Available
    Certification from a registered architect confirming structural plans and compliance.
  • Structural Engineer Certificate Available
    Certification from a structural engineer confirming building safety and load-bearing capacity.
  • CA Financial Certificate Available
    Chartered Accountant certificate on financial status, project cost estimates, and fund utilization.
  • Commencement Certificate Available
    Permission to begin construction issued by the local authority after plan approval.
  • NOCs (No Objection Certificates) Available
    NOCs from fire department, environment, water supply, electricity board, and other authorities.
  • Project Brochure / Specification Available
    Official brochure with unit types, amenities, and specifications. Compare with actual delivery.
  • RERA Compliance Orders Verify Independently
    Check if any orders, penalties, or directions have been issued against this project by RERA.

No reviews yet. Be the first to review this project!

Login to Write a Review

You need to be signed in to submit a review for this project.

Login or Register